After the cottage was razed, and the stakes were placed
outlining the boundary of the new home, it was time to break ground. This was a
very exciting time as my dream was about to begin to take shape. I was building
a large contemporary home with a wall of windows facing the lake front.
Admittedly it was only a hole in the ground, but this hole represented the rough
footprint of my future house. Seeing the hole, I could begin to more easily
visualize my future home.
Digging out the hole and preparing the site for a
foundation is one of the most critical aspects of building a new home. As a
result, I spent several occasions with both the Excavator and Foundation
subcontractors reviewing the house plans and the site prior to, and during the
excavation. It was imperative that all of us were on the same page to ensure
that the foundation walls, with all its jogs and step ups/downs would be located
and installed per the plans. During these meetings a few adjustments were
necessary to the foundation plans, however with all the team members involved
the changes were minor and absolutely necessary. The changes helped prevent more
serious problems later on and ensured that the outside aesthetics of the home
were maintained.
As I already indicated, the foundation is extremely
important to any quality home. If the foundation is not built upon a solid
footing, nor constructed of the appropriate concrete strength, the foundation
walls will crack in short order. These cracks can lead to water in the basement,
settling in the framing, and eventually cracks in the finished walls and
ceilings. Consequently, it is imperative that the excavation site not only be
properly dug out, but also backfilled with crushed stone and sand to provide for
a stable base and to enable proper drainage underneath and around the home. In
my case I had the excavator dig out sufficiently to enable 18” of crushed stone
to be backfilled into the hole and still meet my foundation plan requirements.
Once the site was prepared for concrete, the foundation
crew installed concrete footings 18” wide and 12” deep. In addition they
installed several cement footings in the middle of the house footprint for lally
columns. The footings represent the base of the home and support the concrete
foundation walls and the home itself. Due to the fact that it was winter,
Calcium Chloride was used as an accelerator to speed the curing time of the
concrete. In addition water had pooled in a portion of the hole, so constant
pumping was necessary during the curing time.
After a couple of days, the foundation crew installed forms
for the concrete walls. A day later the foundation walls were poured. Three days
later the forms were removed and the foundation walls were in. I then had my
excavator subcontractor return. After tarring the outer walls, just up to the
level of where the finished grade would be, he installed a perimeter drain
around the foundation and then backfilled the foundation with clean sand and
fill. It is important that boulders and clay not be used as backfill material.
Boulders can crack the foundation walls while being pushed into place, and clay
can lead to improper drainage around the home.
With the foundation in and backfilled I was ready for
framers.
The Framing Stage
The framing stage is probably the most exciting part of
building a home. In a relatively short period of time, literally days, a house
begins to take real form. Within less than a week knee walls were up, floor
joists were installed and a plywood sub-floor was down. After a couple of
weeks, the first floor walls were up and ceiling joists were being installed. I
was so impressed I was convinced my new home was a month ahead of schedule. Boy
was I wrong.
Before I elaborate on my misconception I should jump back
for a minute. While the excavation work went on, I was also engaged with the
Framing subcontractor. The Framing subcontractor needed to order framing
material including lumber, doors and windows, shingles and siding. Inevitably
there were issues with the availability of material and delivery dates, and as a
result, we spent a fair amount of time resolving these issues. Fortunately, due
to constant communication and quick problem solving we were able to have the
initial delivery of lumber arrive on the site within a day after the backfilling
of the foundation.
It is important to note, that it is at this time of the
project that the large outlays of money begin to occur. Lumber costs for a home
construction are quite large, and final payments are due to the Excavator and
Foundation subcontractors. Excavation/Sitework and Foundation installations are
a significant portion of the cost of building a home. In addition, the Framing
subcontractor requires a portion of his labor to be paid in advance.
Also, it is very important that Homeowner Construction
Insurance be obtained prior to the construction phase. This insurance protects
the Homeowner / Builder against material theft and job injuries. All of your
subcontractors and their employees should be insured but don’t count on it.
During any building project, subcontractors are bound to hire extra help for
short stints and I would be surprised if these temporary employees were added to
the subcontractor’s insurance policy. The homeowner/builder insurance policy is
small change compared to the risk of theft or the threat of injury lawsuits.
As I indicated earlier, I was in for a surprise with the
framing phase of my home. As mentioned, the initial framing moved quickly.
However it was still winter and frequent snow storms and extremely cold weather
began to hit. This dramatically slowed progress. In addition, with the fresh
supply of snow it quickly became apparent that my framing crew had an affinity
to snowmobiling. So even on the sunny days my framing crew was frequently
absent. No matter my level of complaining or prodding I was unable to control my
framing subcontractor’s work ethic. Consequently, I had to contact my plumbing,
electric, and fireplace subcontractors to inform them of the delay. This was
extremely painful to have to do, as I had no definitive date on when I would
actually need them and each of them had very full calendars. As a result, to be
able to call them at the last minute and expect for them to drop what they were
doing to come to work on my project was highly unlikely. Again, through regular
communication with these other subcontractors I was able to mitigate some of
this problem, however my project did experience significant schedule slips due
to my framing crews shenanigans.
In retrospect, I am not sure what I could have done to have
prevented this problem. Reference checks on the Framing subcontractor had been
positive. I guess I should have asked what his hobbies were and made sure they
did not correspond to the season I wanted the work done. It is also a fact that
unexpected things do happen on any project and one should expect it and plan
accordingly. For example, put some contingency dollars and schedule into your
project for events such as mine. Also, I can not stress enough to establish a
rapport and regular communication channel with all of your subcontractors. Do
not assume anything during a project of this size.
In Part 3 of “Building Your Dream House”, the Framing
continues and Rough Electric and Plumbing begin. Stay tuned……………
Fill out our 3-5 minute quick and easy form, and receive a free price quote
on custom home building from one of our prescreened and licensed custom home
builders. This process is free and there is no obligation to continue once you
receive your custom home building price estimate.