Instead I picked
up a handful of Home Plan magazines and surfed the internet for home designs. I
also picked up an inexpensive software package for designing homes and floor plans. After a week of reviewing home plans, I found one that met most of
my requirements in terms of a floor plan. The footprint was smaller than I
wanted, but I concluded that I could redraw the floor plan design accordingly using my
newly purchased Home Design Software Package.
The Home Design Software package was not as simple to use
as the instruction manual implied, however after a couple of weeks I had a
floorplan with all the dimensional information.
Assuming the role as the General Contractor
As I had indicated earlier, one of my goals was to assume
the role as General Contractor on this project. I quickly learned that banks
frown upon lending construction mortgages to everyday homeowners and to folks
who have little professional building experience. I got around this issue by
deciding not to use the banks for financing. However, from what I learned later,
it may have been possible for me to assume a construction mortgage if I had quit
my day job and applied for the loan as a “full time General Contractor”. Indeed,
I would have needed to complete a full proposal to the bank with all costs and
subcontractors identified, but this is necessary anyways.
As the General Contractor I developed a build schedule and
task list. Some of the top items included: Identifying subcontractors, pulling
permits, and having a septic design approved.
Carefully Pick your Sub-Contractors
Identifying the right subcontractors is the most important
task a General Contractor performs. Poor selection of subcontractors can lead to
delays in schedules, cost overruns, poor workmanship and strife between the
various subcontractors on the job. Prior to hiring subcontractors, it is
important to visit their current jobsites. Review their work on existing
jobsites and mingle with the other subs to judge the working relationship. In
addition get two or three reference checks on the subcontractors. If there are
poor workmanship, personality issues, or references move on. Do not settle for
second rate subs, even if it means slipping your schedule or costs goals, as you
will more than likely suffer even larger schedule slips or higher costs by
hiring the wrong people.
Pulling Permits
Once you have selected and hired your excavator, chief
framer, and foundation company, review with them your plans. Make sure you walk
the site with them, and carefully stake out the house footprint, paying careful
attention to lot setbacks, septic tanks, leach fields and well location. Once
all are agreed upon with the house plans and the location of the home, contact
the building inspector and review with him/her your plans. You will need to
submit a very thorough package to the building inspector prior to getting
approval. There are frequently town and state forms that need to be filled out
regarding wetlands, and home thermal analysis. In addition, detailed
engineering drawings of the proposed home may be required. In my case the Framer
was able to assist in developing additional sketches of the house plan to ensure
structural compliance to local, state and federal building codes. If I had used
the initial home plans I had obtained, those would have been sufficient. I also
could have contacted an architect with my selected plans to provide additional
details, however it was not necessary in my case.
After about a week and several hundred dollars later I had
the permit to build a new home.
Septic Design
My home required its own septic system on site. As a
result, I required a septic design and an associated permit for the new home. I
recommend pursuing this as early as possible in any new home project as this can
take up to 2-3 months to complete as both town and state approvals are required,
not to mention site and engineering work.
Without knowing exactly where the septic system and tank
will reside, it may be difficult to locate the exact position of the home and in
many cases the building inspector may not approve the building permit until the
septic design permit has been obtained. I was fortunate in that the property
already had a small septic system on the lot, so the building inspector gave me
approval. I was at financial risk, however, in the event the new septic design
was not approved or needed to be repositioned from the proposed location.
Fortunately that was not the case and I was able to move forward on razing the
cottage and beginning site work.
In Part 2 of “Building Your Dream Home”, I will cover
razing an existing building, performing site prep work, and pouring foundation
walls. Stay tuned……………
Fill out our 3-5 minute quick and easy form, and receive a free price quote
on custom home building from one of our prescreened and licensed custom home
builders. This process is free and there is no obligation to continue once you
receive your custom home building price estimate.